Sound Spuds Second Moroccan Well

Monday, August 29, 2016

A second well has been spud on Morocco’s Tendrara Permit by Sound Energy, the TE-7, following the success of the TE-6 well. The well objectives of TE-7 include proving sufficient gas volumes and well deliverability to enable finalization of the field development plan and a concession application and demonstrating the benefits of sub-horizontal drilling, which is expected to be implemented as the production well concept for Tendrara.

The TE-7 site is approximately 830 meters to the Northeast of TE-5 and hence some 1.6 km from the TE-6 site.

Drilling is planned to reach a total measured depth of 3,440 meters with specific tools being used to geo-steer the well at close to an 88 degree angle inside the TAGI reservoir to ensure a horizontal drain of between 600 and 900 meters. The sub-horizontal section will run to the north, parallel to the minimum horizontal stress observed in TE-6.

Drilling and logging of the well is expected to take approximately 54 days according to Sound, with completion and stimulation taking an additional 30 days. Following these two phases clean-up and initial well testing will begin.

An extended well test will follow for approximately 70 days thereafter to confirm production sustainability and to aid comprehensive field development planning.

 