SDX Spuds New Moroccan Well

Monday, November 27, 2017

SDX Energy spud its KSR-16 well development well in Morocco on the Sebou permit. The well is anticipated to take 20-25 days to drill and complete. If successful the well is anticipated to be completed, flow tested and connected to the existing infrastructure.

SDX said the completion activities are expected to be carried out within 21 days of the drilling rig departing the location. This is the third of a nine-well drilling program on the company’s Sebou, Gharb Center and Lalla Mimouna permits in Morocco.

The company also confirmed that its KSR-15 well is currently being connected to the existing infrastructure and is expected to be placed on test production within the next 10 days