Serinus Starts Chouech Es Saida Workovers

Thursday, July 4, 2019

Serinus Energy has started work on its Chouech Es Saida field in southern Tunisia following the field’s reopening. The company started the first well workover on the CS-3 well on June 27.

Serinus said the workover is expected to take two weeks and includes the installation of a new electrical submersible pump. Once completed, the CS-3 well will be brought onto production and the workovers of the other three wells will be performed sequentially.

The company anticipates that all Chouech wells will be on production by the end of August.