Tlou Progresses Lesedi Project in Botswana

Friday, February 23, 2024

Highlights

  • Lesedi 4P and 6P continue to flare gas as dewatering progresses
  • Completion of the crucial 66kV transmission line, connecting Tlou’s Lesedi project directly to both Botswana’s power grid and the broader Southern African Power Pool
  • Connection to Serowe substation achieved, Lesedi no longer isolated from primary Botswana electricity market
  • Lesedi substation which will connect Tlou’s power generators to the transmission line now approximately 38% complete

Lesedi production wells

The Lesedi 4P and 6P production wells are continuing to flow gas as the water level is being gradually lowered to just above the coal. Once the wells stabilize and stop surging (gas and water), gas flow rates will be measured. Tlou is confident that with the in-house knowledge gained from recent drilling efforts, extracting more and more gas out of the coal reservoir will become progressively simpler and more cost effective due to economies of scale.

Transmission line

The 66kV electricity transmission line connecting Tlou’s Lesedi power generation site to the power grid has been constructed and the line has been connected to the Serowe substation.

Any minor finishing works and the addition of switchgear at the Serowe substation will be done prior to the line being energized. The line will be energized as soon as the substation at Lesedi is complete which is expected around the middle of the year subject to funding.

The transmission line is a vital element of the Lesedi project. With the completion of the transmission line, the Lesedi project is no longer isolated from Botswana’s electricity market and is now connected to the broader Southern African Power Pool.

Lesedi Substation

The Lesedi substation, which will connect Tlou’s power generators to the transmission line, is approximately 38% complete. Installation of the earth mat is complete with the control room currently being constructed.

Generators

Gas fired generators will be installed adjacent to the Lesedi substation on Tlou’s 100% owned land. Consultant engineers are evaluating generator options and obtaining quotes from suppliers.

Funding

Tlou Energy is in discussions with several strategic parties to secure the remaining funds required for project completion. The aim is to secure funding this quarter. The Company remains committed to delivering electricity into the grid at the earliest opportunity, with power sales contracted under the existing 10MW Power Purchase Agreement with Botswana Power Corporation.