VAALCO Completes First Well from New Etame Platform

Thursday, December 11, 2014

VAALCO Energy, Inc. saw the completion of the Etame 8-H offshore Gabon. The Etame 8-H is the first development well drilled from the newly installed Etame platform. The well was drilled to a MD of 3,196 meters and penetrated the Gamba Sand reservoir interval at 1,820 meters TVD, contacting 135 meters MD of high quality reservoir within the oil-bearing portion of the Gamba sand. Additionally, the wellbore encountered the current oil-water contact (OWC) at 1,829 meters TVD, resulting in a nine-meter vertical oil column.  VAALCO subsequently shut in the Etame 8-H as the well was determined to be producing hydrogen sulfide (H2S) during the initial testing process.

Investigations are underway to ascertain the root cause of the H2S and develop a plan to produce the reserves in a timely manner.

The contracted jack up rig, the Transocean Constellation II has been moved onto the next location to drill a development well, the Etame 10-H, which is expected to spud in the coming days. The well is targeting the Gamba sand formation in the 1-V fault block in the Etame field, where VAALCO has been producing oil since 2002 utilizing subsea wells. The 1V fault block, which lies south of the main Etame reservoir, has never encountered H2S. The Etame 9-H well, which was to be the third well in the Etame platform campaign, and which is located in the same fault block as Etame 8-H, will be reevaluated in light of the recent results.

VAALCO has already begun the design of a crude sweetening facility that will allow it to redevelop the Ebouri field and provide sweetening capacity for future production from wells producing H2S. As of last month, VAALCO and its partners were targeting a facility commissioning date in 2017. With the discovery of H2S at Etame 8-H, the company is committed to redoubling its efforts to bring the crude sweetening facility on line as soon as practicable.

After drilling the Etame 10-H, the Constellation II will be mobilized to drill three additional development wells from the Southeast Etame/N. Tchibala (SEENT) platform, beginning with a well to be drilled to Gamba formation in the Southeast Etame field where the company drilled a successful exploration well in 2010. The remaining two development wells drilled from the SEENT platform will target Dentale sand formations in the North Tchibala field.